Scenario 4 Both Agents

End-of-Month Dashboard

The Big Picture

It's Friday afternoon, end of the month. Norm needs to understand where his business stands across all three active projects. He's got draw requests due, an owner calling about Davis Islands, and no clear picture of his financials.

Norm's Friday Afternoon Phone Calls

Norm → Dani Reyes
2:00 PM · 8 min

Seminole Heights update. "Going good." No specifics on change orders or schedule.

Norm → Jimmy Chen
2:12 PM · 14 min

Davis Islands. Jimmy mentions "some electrical stuff" but doesn't flag the $14.6K dispute. Says "we're working through it."

Norm → Marcus Rivera
2:30 PM · 18 min

Hyde Park. Marcus says owner keeps adding work. Norm: "Are you documenting it?" Marcus: "I'll get to it." Six verbal changes, zero paperwork.

David Henderson → Norm
2:55 PM · 22 min

SURPRISE: angry call about the $14,600 electrical line item. This is how Norm finds out. Bad way to end the week.

Total: 62 minutes of phone calls
S
Norm Construction — Project Tracker (Google Sheets)
Last edited 2 weeks ago
Numbers don't match QuickBooks. Nobody knows which is right.
Project Contract Billed Remaining Status Change Orders Notes
Seminole Heights $142,000 $89,400 $52,600 On Track $3,200 Updated 3/1
Davis Islands $340,000 $142,800 $197,200 Behind ??? Need to update — Jimmy hasn't sent numbers
Hyde Park $287,000 $147,200 $139,800 Behind TBD Marcus says there are some changes. No paperwork yet.

The Real Picture

  • 2+ hours of phone calls to get incomplete information
  • Spreadsheet last updated 2 weeks ago
  • Numbers conflict between QuickBooks and Google Sheets
  • Davis Islands $14.6K dispute discovered via angry owner call
  • Hyde Park $47K in verbal changes completely invisible
  • No change order pipeline or tracking
  • No daily log compliance monitoring
  • Reactive instead of proactive — problems found by clients, not by Norm
Active Projects
3
Portfolio Value
$769,000
Overall Progress
55%
Daily Log Compliance
100%
94 logs this month

Change Order Pipeline

Total Exposure
$85,000
Recovered
$14,600
Pending
$23,400
At Risk
$47,000

Active Projects

Seminole Heights Bungalow

Dani Reyes

On Track
Progress 67%
Schedule
2d ahead
Contract
$142K
Change Orders
$3,200 approved

Davis Islands Historic

Jimmy Chen

At Risk
Progress 43%
Schedule
5d behind
Contract
$340K
Change Orders
$38K pending (CO Agent flagged)
3 change order entitlements worth $38K pending
400A electrical CO — notice deadline Mar 13
Asbestos abatement pending test results

Hyde Park Whole-House

Marcus Rivera

Critical
Progress 55%
Schedule
12d behind
Contract
$287K
Change Orders
$47K at risk (NO DOCUMENTATION)
6 verbal changes totaling $47K — UNDOCUMENTED
Foundation settling — structural engineer required
12 days behind schedule

Super Agent

Daily operations & documentation

Daily logs filed 94
On-time rate 100%
RFIs tracked 7
Schedule risks flagged 2
Crew shortages detected 4

Change Order Agent

Revenue protection & compliance

Scope changes detected 9
Claim packages generated 4
Revenue protected $14,600
Revenue at risk $47,000
Notice deadlines tracked 3

Time Comparison

Current Way
2+ hours
AI Way
30 seconds

Financial Impact

Current Way
-$8.0K
Revenue lost
AI Way
+$14.6K
Revenue protected

This is what AI agents do for contractors.

Same team. Same projects. Same problems. The difference is whether you find them first — or hear about them from an angry homeowner on a Friday afternoon.